Dealing with Construction Permits

 

DB 2011 Rank 89 DB 2010 Rank 90 Change in Rank up1

 

 

No. Procedure Time to Complete Associated Costs
1 Obtain a certificate to use the land and possibly, one of no objection (certificación de no objeción, certificación de uso de suelo) 7 days DOP 1,080
2 Obtain approval of project design drawings by the Municipal Council, and of the construction license by the Ministry of Public Works and Communications 141 days DOP 97,545
* 3 Receive inspection by the Municipal Council (Departamento de Planeamiento Urbano) 1 day DOP 500
4 Receive inspection by the Ministry of Public Works and Communications 1 day no charge
5 Pay license fees and taxes associated with the construction license and obtain proof of payment 1 day DOP 20,484
6 Obtain recibo de entrada from Ministry of Public Works and Communications 10 days no charge
7 Receive an inspection before the lintel (zapata) of the project is made 1 day DOP 232
8 Receive an inspection before the space between galleries (entrepiso) is completed 1 day DOP 232
9 Receive an inspection before the roof of the project is completed 1 day DOP 232
10 Request water and sewage connection 1 day no charge
11 Receive on-site inspection for water and sewage connection 1 day no charge
12 Receive water and sewage connection 45 days DOP 22,000
* 13 Request electric power connection 1 day no charge
14 Receive on-site inspection for electric power connection 1 day no charge
15 Obtain electric power connection 30 days DOP 55,000
* 16 Receive on-site inspection and connection to telephone 12 days DOP 4,000
17 Notify the Ministry of Public Works and Communications of the building completion, and obtain final approval (inspection) 6 days DOP 1,160